Feb 22, 2008 (newstodate): 2008 will see the certification of Moscow Sheremetyevo Airport's second runway - and the start of designing a new third runway.
The planned new third 3,200 m runway will increase the airport's annual capacity to 35 mio passengers, compared to the airport's total of 14 mio passengers in 2007.
Sheremetyevo has also engaged the British consulting company Scott Wilson to work out a masterplan for the airport till 2030.