Dec 21, 2007 (newstodate): In November, JSC Progresstech and Progresstech-Center completed works on construction of the apron and exit taxiway under the project on reconstruction and development of Vnukovo-1 Airport in Moscow.
The project works included constructing the cast-in-place concrete pavement, sealing the movement joints with airdrome sealant and installing the grounding systems.
The construction covered a period from June to October of 2007 during which an area of 84,000 sq m was paved and joints of 22 m length were sealed.